LEED v5: What’s New in Commissioning?

LEED v5: What’s New in Commissioning?

By Maria Espinosa and Bobby Almeida

The U.S. Green Building Council launched LEED v5 on April 28, 2025. Project registration is now open, and will be mandatory for new projects starting in June 2026.

LEED v5 brings with it several major commissioning requirement changes, as commissioning is now more comprehensive from early design through occupancy. For example, whereas envelope commissioning was previously optional, it is now required. Monitoring-based commissioning is strengthened with long-term performance verification and analytics.

These shifts reflect LEED’s broader move toward measuring actual building performance rather than documentation alone. Below, we outline some of the key changes to expect for LEED v5 projects.

Fundamental Commissioning 

LEED v5 raises the baseline commissioning requirements for all projects by making several activities mandatory that were previously optional or ambiguously defined:

  • CxA engagement during Design 
    • It is now required that the Commissioning Authority (CxA) assist in developing the Owner’s Project Requirements (OPR).
    • The CxA must attend at least one design phase meeting to examine the commissioning design review comments.
  • Mandatory Building Envelope Commissioning
    • Building enclosure (thermal envelope) commissioning is now required as part of fundamental commissioning — no longer limited to enhanced credits.
    • Teams must plan and verify building enclosure performance in accordance with ASHRAE 90.1 requirements.
  • Enhanced Tasks in Fundamental Cx:
    • Projects must have the CxA explicitly do all of the following as part of the prerequisite. These were Enhanced Commissioning activities in prior versions but are now requirements for Fundamental Commissioning:
      • Review submittals of commissioned systems
      • Review the training program
      • Develop an ongoing commissioning plan
  • Additional Required Tasks in Fundamental Cx:
    • Conduct at least one site visit to verify systems are ready for functional testing
    • Attend at least two construction milestone meetings at 50% and 100% completion.
    • There are now additional systems that require commissioning to achieve LEED certification.
  • Alignment with Industry Standards
    • LEED v5 references ASHRAE 90.1 (commissioning language in section 4.2.5) as part of the fundamental requirement, tying commissioning to the current energy code in many states.
    • Projects registered for LEED v5 prior to January 1, 2028 use ASHRAE 90.1-2019, while projects registered after that use ASHRAE 90.1-2022.
 
Enhanced Commissioning 

The Enhanced Commissioning credit in LEED v5 has been updated to reflect modern standards and practices, with updated scopes, paths, and point allocations.

  • MEP Systems Path (Enhanced Cx for MEP): Follow ASHRAE Standard 202-2024 for commissioning new buildings and systems including: systems manual development, additional participation in design and construction meetings, additional OPR requirements, an additional site visit during construction, and a warranty site visit. The commissioning agent must be brought on in the predesign phase or very early in the design phase to meet all Enhanced Cx requirements.
  • Building Enclosure Path (Enhanced Cx for Envelope): Enhanced building enclosure commissioning requires a mandatory mock-up test review, additional site visits, additional testing of completed systems, specific standards referenced for the required tests, plus the additional requirements listed above for the MEP systems but applicable to the building envelope.
 
Monitoring-Based Commissioning (MBCx)

In LEED v5, MBCx transitions to a more rigorous, structured, long-term process. There are two paths:

  • Path 1 —Basic Software:
    Continuous tracking of building energy use with reporting and analytics, confirming performance relative to design intent.
  • Path 2 — Enhanced Software:
    Adds real-time analytics and automated issue detection through the use of automated fault detection and diagnostics (FDD).

A minimum three-year commitment to post-occupancy monitoring is required, while only one year was required in LEED v4. Projects must also provide annual summaries of trends, benchmarks, faults, energy savings opportunities, corrective actions taken, and planned actions. Energy Information System (EIS) platforms must support up to hourly data visualization/reporting for metered systems. Two formal reviews of building systems, equipment, and controls are required during the MBCx performance period.

Building Code Updates & LEED v5 Cx

The 2025 California Energy Code (Title 24, Part 6) and California Green Building Code (Title 24, Part 11, also known as CALGreen), effective Jan. 1, 2026, offer many overlaps with LEED v5 commissioning. In addition to previous similarities, LEED v5 will require the Commissioning Authority (CxA) to review the training plan, in line with CALGreen requirements. The cost premium to provide LEED v5 Fundamental Commissioning should be relatively low for projects already meeting CALGreen code.

The LEED v5 Fundamental Commissioning requirements are based on ASHRAE 90.1, so any jurisdictions utilizing that as their building code will see a major overlap. The only differences will be the few additional items called out in the LEED reference guide, such as submittal review. There are no anticipated overlaps between building codes in these jurisdictions and the additional requirements in LEED v5 Enhanced Commissioning.

IECC code requires basic commissioning of HVAC, HVAC controls, water heating, and lighting systems. LEED v5 Fundamental Commissioning covers all of the requirements in IECC-2018, allowing projects pursuing LEED certification to easily meet code compliance as well.

One major caveat is that all three of the building codes mentioned have exemptions for small projects or certain building types, while LEED v5 has no exceptions to commissioning. This means that smaller projects or projects with minimal HVAC may not require code commissioning but do require commissioning for LEED certification.

Let’s Collaborate!

Interested in LEED v5 certification for your project? Need a Cx expert? Verdical Group is a full-service consulting firm that can help simplify the process. In addition to certification project management, we offer LEED Commissioning (Cx), LEED Energy Modeling, and LEED Daylight Modeling to streamline achieving your team’s sustainability goals. Contact us to learn how we can support your team.